Power factor correction
BSRIA Power quality guide (AG 2/2000) was written by C C Pearson and V Uthayanan and published by BSRIA in July 2000. It states:
Power factor correction is often an important consideration for industrial facilities. Harmonic concerns should always be evaluated as part of a power factor correction evaluation, regardless of whether or not the facility has harmonic-producing loads.
Power factor correction basically involves reducing the reactive power losses, thus reducing the apparent power (i.e. bringing the power factor towards unity).
From the above expressions, the capacitor value for the compensation can be found. This will bring the phase angle ΓΈ between voltage and current to zero, so that the displacement factor to unity. Since the displacement factor is the PF for linear loads, it can be improved to unity using capacitor compensation. But for the non-linear loads, the distortion factor should be improved to unity as well as the displacement factor in order to bring the PF to unity. To do that, we need to eliminate all the harmonics using harmonic filters.
--BSRIA
[edit] Related articles on Designing Buildings
Featured articles and news
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
How orchards can influence planning and development.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.